Ranking and comparing key factors causing time-overruns in on-site construction
For years, the construction industry has looked for ways to avoid time-overruns in construction. Despite previous research mapping the factors affecting time performance, site-managers have difficulties in reducing the time-overrun. In order to create a clearer guidance on how to control time-performance, this study investigates the resource related factors because they are within the site-manager’s control. Three Case studies were followed and a survey including 36 participants where conducted. Both investigated and ranked the likelihood of delay due to the seven different resource factors. The ranking of the resource factors was identified as: (1) Construction design, (2) Connecting works…